Building pad is prepared
Foundations for the interior steel columns and the perimeter tilt-wall panels are installed

 

Floor slab is formed up and poured
Tilt panels are formed on the floor slab and poured outside face down against the slab

 

Braces are attached once panels have cured
Panels are lifted into place

 

The erection process continues until all of the panels have been erected and braced to the floor
Process may take several days depending on the size of the building.

 

Steel structure is tied into the panels once a section of the tilt wall has been placed and plumbed

Panel bracing is removed when the steel structure is adequately tied in and braced

 

Erection of the interior portion of the steel structure is often begun prior to the completion of the setting of the panels for larger buildings, reducing the time to close in the building

 

Outside face of the tilt-wall panels, which were cast face down, are cleaned and touched up in preparation for painting and other finishing applications

 

Application of finishing touches such as painting, trim, windows, doors, canopies, landscaping and sidewalks are completed